WSOR Reedsburg and Cottage Grove Subdivision

Project Information

Owner

Wisconsin and Southern Railroad

Engineer

Brent Marsh

Location

Madison, WI

Contractor

Confidential

Technical Description

Product: Tracktex (82ft x 12.8ft)

Share

Introduction

The Wisconsin & Southern Railroad Cottage Grove Subdivision Trackbed Rehabilitation project provided drainage improvements, trackbed rehabilitation and ballast replacement. TrackTex Anti-Pumping Geocomposite was selected as the best solution to the mud pumping of fine sediments into the newly placed trackbed ballast while maintaining overhead clearance specifications.

This project consisted of several areas where drainage improvements and trackbed rehabilitation were required. The mainline trackbed had been lost due to sediment fines pumping up during wet conditions and contaminating the ballast. The fines mixed with the ballast and weakened it, which caused track issues underneath the I-39 overpass and Beltline Areas. After Engineer assessment it was decided the track structure needed a replaced ballast to support train loading. Maintaining an overhead clearance under the Interstate overpass presented a further challenge.

There were two areas (Beltline & Interstate) that required ditching and undercutting to improve drainage away from the track, as well as ballast replacement. The historic issues caused by mud-pumping meant a solution was required to prevent recurrence and various options were considered.

 

How TrackTex helped

Following technical support from Geofabrics, TrackTex Anti- Pumping Geocomposite was proposed as a solution to the mud pumping of fine sediments into the newly placed trackbed ballast.

 

Mud-pumping choked the trackbed with sediment fines, causing drastically reduced bearing strength

 

The first area (Beltline) under construction was a 700’ section. Ditching and undercutting work showed that this was a rock cut area, meaning construction depths were shallow and close to the original trackbed. After removal of the track and the excavation was completed, TrackTex was installed, new ballast laid and the tracks reinstated. Tracktex prevents any sediment fines from pumping into new ballast while allowing the upward passage of water when under pressure caused by train loading. This reduces maintenance required to provide proper drainage to the new constructed ditches and preserves the long term strength of the ballast.

 

Tracktex allows pore pressures to dissipate under loading while preventing migration of fines

 

The second area under construction was a 300’ section of trackbed including an Interstate 39 overpass. This section was heavily contaminated with undrainable clay and silt fines. Some of the trackbed did not have any visible ballast and was directly below the overpass. Due to railway specifications a minimum of 23’ headroom had to be maintained, meaning the designed excavation required removal of up to 12” of soil after the track was lifted. Following the excavation TrackTex Anti-Pumping Geocomposite was installed and then 6-8 inches of ballast was placed. The rail and sleeper ties were placed over the ballast to be realigned. Finally after realignment of the track rail ballast was placed and tampered to finish this section of the project.

 

Ballast saturated with fines as a result of mud- pumping degrades quickly

The Outcome

Tracktex is a microporous geocomposite which allows water to escape when under pressure, but remains impermeable without pressure so provides a barrier to prevent saturation from rainfall.

 

Up to 12” of soil had to be excavated to meet the height restrictions for the interstate overpass

 

The cyclic loading from axles passing allows dissipation of pore pressures, which facilitates desiccation of any existing subgrade slurry. This drying out of the formation means that over time Tracktex actually improves the quality of the track formation by increasing the modulus.

 

Tracktex allows water to escape which facilitates desiccation of the slurry so improves the formation over time

 

The thin build up required to meet the height restrictions means little protection can be provided to the membrane. Tracktex has been designed to work in these aggressive conditions so is sufficiently robust for both installation and operational phases. It is also flexible enough to conform to an uneven subgrade to ensure no slurry forming voids exist.

 

TrackTex prevents mud pumping so maintains the integrity and strength of the ballast

 

This robustness gives Tracktex a long operational life, and it has been shown to extend maintenance intervals due to pumping failure by more than 25 times providing significant savings over any available alternative for mud- pumping failure.

 

TrackTex was installed without the need for any specialist equipment.

 

Installation is straightforward and requires no specialist equipment. This simplicity makes for an easy and fast installation and so avoids risk of delay when on site, even when dealing with challenges such as restricted height.

 

The robust nature of TrackTex allows straighforward and
fast installation

Tracktex is the result of research and development over many years undertaken in conjunction with Rail Authorities, Contractors, Designs and other industry experts. Geofabrics have been manufacturing and supplying the rail industry with track rehabilitating geotextiles and geocomposites for more than 20 years.

Tracktex was developed utilising a full scale, purpose built test facility to simulate mud-pumping failure in the most extreme conditions found in trackbed. It is a unique, patented geocomposite, and since gaining approval in 2010 Tracktex has been actively used in live rail with more than 7 million ft2 having been installed.

 

Latest

Discover Our Case Studies

Explore our latest case studies showcasing our expertise.

Chicago Transit Authority Blue Line

The CTA Blue Line upgrades in 2023 presented some challenging ground conditions in a tight, urban setting. A solution was needed to deal with low CBR subgrade while keeping to shallow construction ...

Diamond Crossing Replacement with TrackTex

In Detroit Lakes, MN, a frequently trafficked diamond crossing operated by Canadian Pacific and BNSF had experienced frequent fouling because of mud-pumping. Mud pumping results in ballast failure,...

Coos Bay Line Tunnel 21 Rehabilitation

The Coos Bay Rail Line is owned and operated by the Port of Coos Bay. It spans 134 miles from Coquille Oregon to Eugene Oregon, providing connections to the North American rail network for manufact...
Preventing Mud Pumping, Ensuring Track Stability

Comprehensive Services for Track Stability and Performance

At TrackTex, we offer a range of services designed to address the challenges of mud pumping and ensure the stability and performance of your tracks. Our team of experts utilizes advanced techniques and technologies to deliver effective solutions tailored to your specific

Professional Development Hours

GEOfabrics continuing education sessions provide technical training on specifying and using TrackTex. These sessions contribute to PDH hours.

Trackbed Stabilization

Geosynthetics are widely used as a way to improve ballast performance under railways. GEOFabrics RK4 is a geocomposite comprising a stabilizing geogrid bonded to our RK1 needlepunched non-woven sep...

Symptoms of Mud Pumping

The symptoms of Mud Pumping are similar to those of life expired ballast, i.e. wet spots appearing at the surface of the ballast accompanied by rapid deteriorating of track geometry. However, from ...